Realignment of QEW westbound lanes, widening and rehabilitation of the Dundas Street overpass of Highway 403, and rehabilitation of QEW westbound off-ramp and structure over Hwy 403 at Ford Drive.

Key Elements:

  • Single span, 40 m rigid frame structure for QEW westbound over Hwy 403; cast-in-place deck
  • Earth excavation (55,000m3), granular placement (110,000t,)
  • Extension of 9m arch culvert at Joshua Creek
  • Asphalt removal, waterproofing, repair of deck surface and bearings, asphalt resurfacing, reconstruction of deck ends
  • Barrier wall replacement
  • Storm sewer installation (1800 m), drainage structures (60)
  • Electrical, lighting, and Advance Traffic Management System (ATMS)

Contract Type

Design Bid Build (DBB)

Client

Ministry of Transportation Ontario

Contract Administrator

McIntosh Perry Consulting Engineers Ltd

Owner

Ministry of Transportation Ontario